Standard operating procedure: Adding a new site to the network
I wrote this one the way I'd ideally do it: sit with the engineer who actually runs this procedure and write down what they do, rather than repeat what the old page claimed. In practice the two wouldn't fully match – more on that in Finding and Fixing a Broken Process.
Owner: Network Infrastructure (site provisioning) · Backup owner: Change Management lead Last reviewed: 2026-06-15 · Next review due: 2026-09-15 Status: Active
This follows the standard procedure template from the Ownership and review model – Owner, Last Reviewed, Purpose, Scope, Prerequisites, Procedure, Rollback, Related pages, in that order. Same layout on every runbook means readers don't have to relearn the page structure when switching to a different one.
Purpose
This procedure provisions a new site – an office, data centre, or remote point of presence – onto the corporate network, from initial network allocation through to go-live and handover to operations.
Scope
This procedure applies to physical sites that require WAN connectivity, a local network, and integration with existing monitoring and access control. It doesn't cover cloud-only or virtual-site deployments; see Provisioning a Cloud Region for that procedure.
Prerequisites
- Site has an approved entry in Projects & Change Log, with a project sponsor named
- IP address allocation requested and approved by the addressing team
- Site has physical network hardware installed and powered (site build team owns this)
- Change request raised and approved per the Change Management Process
- Access to the site's management VLAN confirmed
Step-by-step procedure
-
Confirm the IP allocation. Check the addressing team's record and note the assigned subnets.
Caution: Don't provision against a tentative or preliminary allocation. If the confirmed range differs, steps 2–4 must be redone.
-
Configure the site router. Apply the standard config template (
site-router-base-config). Update the hostname, management IP, and subnet declarations to match the allocation. -
Establish WAN connectivity. Bring the WAN link up per the provider's activation instructions, then confirm it's passing traffic with a basic reachability test to the nearest core site.
-
Configure routing. Advertise the new site's routes into BGP, the WAN routing protocol in use (see Architecture & Design → WAN Routing Overview). Confirm propagation by checking the routing table on an adjacent core router.
-
Enable monitoring. Add the site's devices using the standard device template, then trigger a test alert to confirm it reaches the on-call channel.
Important: Don't skip this step, even under time pressure. Missed monitoring has previously delayed incident detection on this site.
-
Apply access control and firewall policy. Apply the standard site ACL and perimeter firewall ruleset, restricting management access to approved jump hosts per Naming Conventions and Access Standards.
-
Validate end-to-end. From a test device on the new site, confirm all of the following:
- Internet and internal application access work as expected.
- The site appears correctly in the monitoring dashboard.
- Management access via the jump host succeeds.
-
Hand over to operations. Update the site's entry in Architecture & Design with the final config summary and topology diagram, then notify operations via the standard handover checklist.
Rollback steps
If validation fails and the issue can't be resolved within the change window:
- Remove the site's routes from the WAN routing configuration.
- Disable the site in monitoring, so it doesn't generate false alerts.
- Revert the site router to its pre-provisioning state (factory config, powered but unconfigured).
- Update the change request with the rollback reason and notify the project sponsor.
- Log the failure and root cause in Projects & Change Log, so the retry starts with that context instead of repeating the same mistake.
Related pages
Italic items below are pages that would exist in a real documentation space (architecture references, policy pages, other runbooks) but aren't part of this portfolio sample, so they aren't linked. Linked items point to real pages on this site.
- Ownership & Review Model – ownership and review policy for this page
- Finding and Fixing a Broken Process – why site provisioning procedures need checking against what engineers actually do
- Architecture & Design → WAN Routing Overview
- Policies & Standards → Naming Conventions and Access Standards
- SOPs / Runbooks → Change Management Process
- Troubleshooting & Knowledge Base → Common Site Provisioning Issues